Service & display
Reference & limitations 5 end routes unresolved
3D routing status
79 visible routing guides cleared the assembled solid-geometry check. 5 unresolved paths are withheld from the 3D view and listed below. Their functional connections remain in the wiring diagram; they are not verified physical routes.
Connections still needing a physical route
- stack negative / neck transition TBD: End transition or interface path has not been geometrically routed.
- stack positive / neck transition TBD: End transition or interface path has not been geometrically routed.
- Protected auxiliary feed to front regulator / leg 1 logical guide: End transition or interface path has not been geometrically routed.
- Protected auxiliary feed to front regulator / leg 2 logical guide: End transition or interface path has not been geometrically routed.
- Shared isolated COM link to front monitor controller / neck transition TBD: End transition or interface path has not been geometrically routed.
There is no artificial wire-thickness expansion. Endpoint contact regions and connector internals are conceptual allowances, not selected or rated terminations.
One service channel / separate power and communication lanes
This panel explains the approved 9S61P connection scheme and proposed fixed-dock service layout. One trapezoidal trough has no internal divider. It carries distinct POWER and ISOLATED COM harness courses. Short cartridge-local connections meet the core-mounted docks; long power cables and the communication harness stay with the core when a cartridge is removed. This remains an engineering discussion reference, not a rated construction schematic.
Fixed local docks / every cartridge remains a separate service unit
Red and slate distinguish the series power circuit. Blue shows the separate isolated-monitoring harness course in the same overall channel. A shared route does not join cartridge grounds or make the power circuit parallel. Line widths are graphical, not cable dimensions or ampacity. Scroll horizontally on a small screen.
Inside each cartridge / short local connections
Positive cell terminals connect through individual fusible-link allocations into the positive collection layer; negative terminals connect to the separate negative collection layer. The monitoring allocation uses its own cartridge-local protected supply. Voltage, representative cell-temperature and fuse-status connections stay short inside that cartridge, then reach its local dock communication interface. They do not connect directly to one common stack supply or join local cartridge grounds. Busbar material, joining process, insulation, vent clearance and terminal stack allowance remain to be engineered.
Individual cell fusible links approved / ratings unassigned
F-C01-01 through F-C09-37 identify 549 individual positive cell-link allocations. The cartridge-output fuse remains a separate function. Cell-link dimensions, opening current/time, interrupt rating and coordination are unassigned; these symbols do not establish thermal-runaway containment.
Auxiliary power / W-AUX+ and W-AUX−
Regulator input/output range, power, grounding and isolation are unassigned. The high-current rover output bypasses the PCB.
Data / D-SRD
The base plug is the power interface. The local SRD link carries configurable digital I/O; the rover provides the Supervisor radio link.
Connection legend / separate power and return conductors
Each positive cell terminal → its individual fusible link → the cartridge positive collection busbar → cartridge fuse/isolation → the short series jumper network → main protection/service disconnect → base-plug positive. There are 37 individual cell links in each parallel group and 549 across the nine cartridges; they are parallel cell branches, not 549 fuses in one series conductor.
Separate negative collection busbars complete each cartridge connection. C01− provides the stack-negative end through the protected return allocation to the base-plug negative. The return rail is a dedicated conductor, not the chassis or core casing. Individual cell fusible links and cartridge fuses serve different fault paths; neither is a demonstrated guarantee against thermal runaway or propagation.
Shared-channel proposal: a trapezoidal trough has a POWER section for two 8 mm outside-diameter packaging targets and a distinct ISOLATED COM section for the paired monitoring-harness allowance. Long harnesses and docks stay core-mounted; cartridge-local leads end at D01–D09. There is no internal divider. Harness spacing, retention, electrical isolation and electromagnetic performance remain engineering requirements. Actual dock mating direction, retention, contact layout, feedthroughs, cable gauge, end-neck transitions and bend radius remain unvalidated.
| Reference | Connection / function | State |
|---|---|---|
| C01–C09 | 61-cell cartridges, including local monitoring, temperature sensing and approved fuse/isolation allocations | 1S61P connectivity approved; hardware provisional |
| J01–J08 | C01+ → C02− through C08+ → C09−; eight fixed-dock series jumpers; no common parallel power rail | Polarity keying, connector design and ratings unassigned |
| W-P+ / W-P− | C09+ / C01− to the main protection and service-disconnect function | 32.4 V nominal; fault-current and switching design pending |
| W-OUT+ / W-OUT− | Protected power rails to the base plug and rover distribution | 69.3 A continuous / 136 A peak low-voltage load case; gauge and pinout unassigned |
| W-AUX+ / W-AUX− | Protected rails to regulator, then PCB and SRD electronics | 60 W combined electronics allowance; regulated voltage unassigned |
| M01–M09 / T01–T09 | Per-cartridge monitoring/protection and cell-temperature functions | Signal protocol, local reference and floating-domain isolation unresolved |
| D-SRD | PCB ⇄ local SRD ⇄ rover; rover backhaul ⇄ Supervisor | Functional communications path; no RF performance claim |
Provisional vehicle electrical load case
Chosen for this reference: six brushless wheel motors at 250 W electrical input each continuously, or 500 W each for a 10-second example peak, plus 60 W total core/rover electronics. These are assumed battery-side demands, not motor specifications or a prediction from rover mass. Several hundred kilograms on the Moon does not establish power without speed, terrain, slope, wheel radius, gearing and traction data.
| Reference load | Continuous | 10-second example peak |
|---|---|---|
| Six wheel motor electrical inputs | 6 × 250 W = 1,500 W | 6 × 500 W = 3,000 W |
| Electronics allowance | 60 W | 60 W |
| Total battery-side budget | 1,560 W | 3,060 W |
| At 37.8 V calculation point | 41.3 A | 81.0 A |
| At 32.4 V nominal | 48.1 A | 94.4 A |
| At 22.5 V theoretical low boundary | 69.3 A | 136.0 A |
Current is P/V before wiring losses. The 22.5 V point is nine times 2.5 V for sensitivity analysis; it is not a selected operational cutoff or a recommended discharge strategy. This budget excludes excavation/drum power, heaters, charging, regenerative braking and additional conversion losses. The 10-second interval is an assumed comparison duration, not a validated duty cycle.
Main power conductor comparison / not an ampacity selection
Comparison basis: copper at 20°C, resistivity 0.017241 Ω·mm²/m and 2.0 m total current-path conductor length. R = ρL/A; drop = IR; heating = I²R. Actual path length, eight series jumpers, contacts, fusible links and busbars add resistance.
| Copper area | Equivalent solid bare diameter | Resistance / 2 m | Drop at 136 A | Resistive loss at 136 A |
|---|---|---|---|---|
| 10 mm² | 3.57 mm | 3.448 mΩ | 0.469 V | 63.8 W |
| 16 mm² comparison basis | 4.51 mm | 2.155 mΩ | 0.293 V | 39.9 W |
| 25 mm² | 5.64 mm | 1.379 mΩ | 0.188 V | 25.5 W |
No row establishes allowable current. Strand packing and insulation increase diameter. An 8 mm insulated outside diameter for the 16 mm² comparison is a packaging target only, not a selected or rated cable specification. A single trapezoidal channel in the cartridge crescent space reserves distinct POWER and ISOLATED COM sections. Geometry, wall continuity and cartridge extraction are checked separately from electrical performance. The side-by-side paired communication course, end-neck transitions, dock/feedthrough details and cable bend radius still require coordinated design. Power lines in the 3D reference explain connectivity; a proposed channel or cable envelope does not establish installed cable performance.
Vacuum, insulation, wire temperature, bundling, mounting heat paths and termination temperatures determine the needed thermal derating. At 69.3 A, the same 16 mm² / 2 m copper example dissipates 10.4 W before connections. Hotter copper increases resistance. The actual cable, connector and fuse set still requires coordinated electrical, thermal and packaging design.
Sources: Copper IACS resistivity · NASA wire derating and thermal modelling.
Shared route / electrically separate domains
The user-requested simplification is mechanical: local cartridge functions connect at their nearby dock, and the paired isolated communication harness follows the power harness in another section of the same overall trough. Isolation hardware and the actual link architecture remain unselected. The channel has no divider; electrical isolation and immunity to motor switching noise still require the appropriate interface and installation design.
Short local monitor branches and a shared paired-harness course replace the earlier nine long individual blue routes. A future isolated daisy chain would use successive point-to-point segments; an isolated multidrop bus would require a different selected interface. This reference intentionally specifies neither circuit. Cable construction, spacing, twisting, termination and electromagnetic testing remain engineering inputs.
Architecture examples only: TI isolated monitor-chain architecture · ADI isolated twisted-pair link description. These examples do not select devices suitable for the present 1S-per-cartridge arrangement.
Inputs needed before this becomes a rated wiring reference
Confirm the 9S operating voltage window and actual continuous/peak motor and electronics loads; real peak duration and regeneration/charging behaviour; cable lengths and permissible voltage drop; insulation, connector and thermal conditions; selected protection devices and fault-interruption requirements. The main cable size cannot be derived from the cell count or a cell’s discharge-current listing alone.
Service is de-energized: isolate and verify power off, unmate the selected cartridge at its proposed dock, then open the housing or lift the cartridge. The fixed dock, long power harness and COM harness remain with the core. The dock is a mechanical/electrical interface allocation, not a catalog connector or live mating design. Hot swapping, a communication bypass with a dock disconnected, and continued operation with a removed cartridge are not claimed.
Context: Molicel M65A nominal cell data · NASA on parallel-cell isolation and propagation · TI on battery monitoring functions. These sources do not validate this proposed pack.